Data center lift and shift is the fastest way to relocate your IT infrastructure when leases end, facilities upgrade, or sites consolidate. Moving servers, racks, and networking exactly as they are gets you operational at your new location in days instead of months. At One World Logix, we have executed over 100 relocation projects across India and 30 countries with a documented record of zero data loss. Our end-to-end services cover everything from dependency mapping and anti-static packing to climate-controlled transport and precise re-cabling. Whether moving five racks locally or two hundred across states, we apply the exact same disciplined engineering process. We take this rigorous approach because there is absolutely no room for improvisation with your mission-critical infrastructure.
Lift and shift (also called rehosting) means physically relocating your existing infrastructure as-is — same servers, same configurations, same architecture — to a new location. Nothing is redesigned, virtualised, or moved to cloud. What ran in the old facility runs identically in the new one.
A fast, low-risk physical relocation of your systems as-is—ideal when only your location needs to change.
May include cloud moves, consolidation, virtualisation, or re-architecting. Bigger transformation, longer timeline.
Our team assesses your environment and recommends honestly — see our complete data center migration services for full-transformation projects. Relocating IT infrastructure is a critical step that requires careful planning and flawless execution.
Whether you are consolidating facilities or moving to a new colocation, we manage the complex logistics from start to finish. The physical lift and shift approach minimises downtime by relocating your existing servers exactly as they are configured.
We provide specialised anti-static packaging, secure climate-controlled transportation, and precise re-racking at your destination. Reach out today to schedule a free consultation for your data center lift and shift project.
Planning & Integrations...
Project Management...
Office Turnkey Projects...
Assembling & Dismantling of Assets...
Packing & logistics Management...
Risk Management...
Heavy Machinery (UPS) integrations...
Technical Support...
Our team assesses your environment and recommends honestly — see our complete data center migration services for full-transformation projects. Relocating IT infrastructure is a critical step that requires careful planning and flawless execution.
Whether you are consolidating facilities or moving to a new colocation, we manage the complex logistics from start to finish. The physical lift and shift approach minimises downtime by relocating your existing servers exactly as they are configured.
We provide specialised anti-static packaging, secure climate-controlled transportation, and precise re-racking at your destination. Reach out today to schedule a free consultation for your data center lift and shift project.
Both facilities surveyed — power, cooling, floor loading, access routes, rack space
Complete asset inventory: make, model, serial number, rack/U position
Application and network dependency map — nothing gets unplugged in the wrong order
Written project plan with timeline, move windows, and rollback path — before work begins
1. Every cable labelled at both ends with colour-coded tags before disconnection
2. Rack elevation diagrams created to mirror the layout at the new site
3. Client-side backups verified — we do not move until restores are tested
4. Configuration exports for network devices — full restore possible if needed
ESD wrist straps and grounding mats throughout — static protection is non-negotiable
Servers removed in reverse installation order, rails and accessories bagged and labelled
Documented shutdown sequence — applications, then servers, then network, then power
Military-grade ESD bags and foam-lined flight cases sized to each unit
Air-conditioned, anti-vibration vehicles held at 18-22°C throughout transit
GPS-tracked, security-sealed, dedicated direct movement — no shared loads, no depot stops
UPS, then PDUs, then network, then servers — verified by certified electricians
Cabling follows the colour codes from Stage 2 — every cable to its documented port
Re-rack to the documented elevation diagrams — every server in its planned position
All systems pinging, VLANs routing, connectivity confirmed
level tests against the pre-move baseline
asset register, cable maps, updated elevations — then formal sign-off
Rack-mounted and blade servers (Dell, HP, Lenovo, Cisco, Supermicro) | populated racks and cabinets 12U-48U | SAN/NAS/DAS storage arrays | switches, routers, firewalls, load balancers | UPS systems and PDUs | KVM switches, patch panels, tape libraries | structured cabling — and the complete server room, end to end.
Years of Experience
Data Center and Server Projects
Data Loss
One World Logix is ISO 9001:2015 certified, GEM empanelled for government contracts, MSME registered, IAM member, and IAF certified — a credential set no general mover in this space can match.
Our clients include banks, hospitals, IT services companies, telecom operators, and manufacturers — organisations where downtime is measured in lakhs per hour, and where the move simply has to work the first time.
We provide data center lift and shift services in Mumbai, Navi Mumbai, Pune, Delhi NCR, Bangalore, Hyderabad, Chennai, Ahmedabad, Kolkata and 25+ cities pan India — plus international lift & shift to the UAE, Singapore, USA, UK and 30+ countries with full customs documentation.
Data center lift and shift is the physical relocation of existing IT infrastructure — servers, racks, storage, and networking — moved as-is to a new facility without redesigning any system. One World Logix provides end-to-end lift and shift services across India with zero downtime
Lift and shift moves your existing systems unchanged to a new location. Full migration may also include cloud moves, consolidation, or re-architecting. Lift and shift is faster and carries no configuration risk, because nothing changes except the address.
A small server-room lift and shift can complete over a single weekend. Larger multi-rack projects typically run 3-10 days in phased windows. One World Logix provides a written stage-by-stage timeline after the free site survey.
Yes. We use phased move windows, verified backups, parallel running where possible, and pre-agreed rollback plans — so critical operations continue while infrastructure moves in controlled batches.
What does data center lift and shift cost in India?
Yes. We follow chain-of-custody documentation, ESD anti-static handling, sealed and GPS-tracked transport, and client-verified backups before any equipment is powered down.
Yes. We handle same-building moves, cross-city relocations, interstate projects across 25+ Indian cities, and international lift and shift to 30+ countries with customs support.